The District immediately responded once it discovered the spill at approximately 8:24 a.m. Flow in the pipe was stopped by 8:40 a.m., and by 9:15 a.m. on February 17th, District staff had created a barrier with spilled solid material to stop spillage into the tributary. The District used a Vactor truck to vacuum the wastewater at the spill point to further eliminate discharges to the tributary and capture pooling wastewater on the ground at the spill site. A tractor was used on the service road at the spill site to gather solid waste and then that waste was removed using a dump truck supplied by Goleta Sanitary District. The Vactor truck disposed of twelve loads of collected wastewater at the regional treatment facility.
At approximately 3:00 p.m., the District collected water samples above, at, and below the discharge spot in the tributary. District staff also gathered foreign material by hand throughout the spill site, including carefully removing materials by hand from a vegetated area closest to the tributary bank.
Between 5:55 p.m. to 6:05 p.m. that same day, the District was able to notify the appropriate agencies without substantially impeding the spill response.
On Sunday, February 18th, District staff returned to the spill site to continue clean-up efforts until rain commenced. Rain continued through Monday, February 19th, with over 3 inches of rain falling in the area.
On February 20th, a contractor mobilized to repair the force main, and on the 21st the contractor carefully excavated the section of failed pipe. Wastewater remaining in the pipe was pumped out of the pipe with mutual aid from the City of Santa Barbara, Goleta Sanitary District and Marborg Industries. The failed section of the pipe was removed and replaced with new pipe and repair couplings per District Standard Construction Specifications. The contractor backfilled the new pipe on February 22nd.
In March, the District removed an additional 10.35 tons of spill solids using hand tools from the upland area and reseeded the disturbed upland area with professional guidance from environmental consultants and a local ecologist, in coordination with the Santa Barbara Airport. In total, the District recovered and removed approximately 68,961 gallons of spilled wastewater plus additional semi-solid and solid materials in February and March. The District also reseeded the disturbed upland area to restore vegetation. The District also temporarily installed straw wattles between the disturbed upland area and the tributary out of an abundance of caution to prevent any erosion during forecasted rain events.
On March 21st, the District presented an update to the Goleta Slough Management Committee and requested agency involvement in a future inter-agency communications roundtable. The District has updated its communications plans and continues to coordinate with other agencies to ensure it has the most up-to-date contact information.
During the first week of April, the District conducted a successful hydrostatic pressure test on the 24-inch force main. The test was done as a precaution and further investigation into whether the pipe is stable for recommissioning. This test was the culmination of several weeks’ worth of preparations with several independent engineers and professionals. The results of the test indicated that the 24-inch force main meets sound engineering criteria and could be successfully placed back in service. As a result, the District, with support from independent engineers and in coordination with the Santa Barbara Airport, successfully recommissioned the 24-inch force main on May 1st.
The District has continued sampling and monitoring water quality in the tributary, Tecolotito Creek, and the Goleta Slough. The District staff also completed updated training on the District’s Spill Emergency Response Plan (SERP) with an independent consultant, which included training on a few updates.